Giga Press Mounts Appear at Tesla's Texas Optimus Factory in New Drone Footage

Four reinforced foundations are being fitted with IDRA press mounts — Tesla has not said what they will cast.
New drone footage from Tesla's Optimus factory at Giga Texas shows crews fitting frame mounts into four reinforced foundations on the southeast side of the building, ahead of the concrete pour. Giga Texas observer Joe Tegtmeyer, who flies the site with Tesla's permission, identifies the mounts as bases for IDRA Giga Press casting machines, in the same format used for the casting section of the main Giga Texas factory. Tesla has not confirmed the equipment or said which parts would be made at that end of the plant.
The foundations first appeared in footage from November 18, when the building's main steel structure stood at roughly 65 percent assembled. The November 20 flight shows the next step: metal mounts set into the rebar before concrete is poured around them. IDRA supplied the large casting machines Tesla uses for Cybertruck underbody castings at the same campus, and the foundation layout at the Optimus plant matches that heavy-equipment pattern rather than ordinary floor slab work.
Why a robot factory would need a casting machine built for car bodies is the open question. IDRA Giga Press specialist Luca Greco, whose assessment Tegtmeyer published alongside the footage, describes the likely logic: instead of running several smaller presses of 400 to 1,500 tons of clamping force, Tesla could run a single machine of roughly 6,000 tons fitted with a die holding dozens of cavities, casting many Optimus structural parts or housings in one shot. The approach would cut part count and cost at the volumes Tesla is targeting, but Greco flags the engineering cost: molten metal must reach every cavity evenly, and a die for a press that size can weigh 50 to 100 tons, making uniform temperature control across all cavities difficult. That reading is expert interpretation of the footage, not a Tesla statement.
The Texas plant is Tesla's volume play for Optimus. In its October quarterly update, Tesla said production of its first production-quality Optimus robots had begun on high-volume lines in Fremont, California, while the Texas factory remained under construction. Chief financial officer Vaibhav Taneja said in October that the Austin plant is intended to make more robots than the California line. Casting capacity of the kind the foundations suggest would fit that sequence: Fremont proves the design and the line, Texas industrializes the parts supply behind it.
What the footage establishes is narrower than the speculation around it: heavy casting foundations are going into the Optimus factory floor, in a building whose steel is about two-thirds up. Whether those presses cast robot housings, structural frames or something else entirely is a question Tesla has not answered. The pour comes next, and with it the first hard evidence of how Tesla intends to manufacture humanoids at car-industry scale.