Concrete Poured for All Four Giga Presses at Tesla's Texas Optimus Factory

Drone footage shows fresh concrete in all four press foundations and the steel frame about 60% complete at Austin's plant built for Optimus at scale.
Fresh concrete now fills all four foundations for the giant casting presses at Tesla's Optimus factory in Austin, Texas, and the building's steel frame is about 60 percent complete, according to a November 27 drone update from Giga Texas observer Joe Tegtmeyer. The concrete is the visible change since the last flyover, when crews were still preparing the four bases and setting the mounting frames into rebar.
The four slabs are the mounts for Giga Press machines, which force molten metal into moulds to produce large castings, a process Tesla already uses for vehicle parts. Tegtmeyer expects the presses to make robot parts in volume once the factory is running. The latest flyover also shows the building taking shape: much of the frame stands four storeys tall, with a more open structure on the east side.
Outside the building, crews are widening and reinforcing the ground and preparing a new road. Tegtmeyer expects the steel work to finish around the end of March 2027, his own estimate for the frame rather than a company date.
The Austin plant is the second half of Tesla's Optimus manufacturing plan. The company's October quarterly update listed the Texas site as under construction and said its Fremont, California, line had built the first production-quality Optimus robots. The Texas factory is intended to produce robots at a larger scale. The update landed the same day Tesla's plan to buy gear-maker EMAG's assets became public in Germany, another step toward building Optimus in volume.
The next public look at the robot itself could come before the factory is finished. Musk said earlier this month that Tesla could show what it is like to interact with Optimus in a month or two, putting a possible demonstration between mid-December and mid-January. Tesla has not set a firm date.